FMB InsiderThe Public Record

Happening Now

What's actually going on at Fort Myers Beach

Is the pier back? Is Times Square rebuilt? What's open? These are the questions everyone asks and almost nobody answers with current, sourced information. This page does — and it says plainly when something isn't back yet.

Latest from the Town of Fort Myers Beach

Live feed

Straight from the Town's official announcements — refreshed automatically.

Source: Town of Fort Myers Beach — News Flash

0
permits issued in the last 30 days
2027
expected completion of the new pier
1
permanent Times Square building approved since Ian
Total documented investment in the island
$1.49 billionand climbing

Documented from the Town's building-permit record through August 14, 2026; updated as new permits are issued.

$256.5 million
Public & government
$675.6 million
Businesses
$562.7 million
Homeowners

Big public projects, private developments, and — added up from the town's building permits — what individual owners are pouring back in. Every figure traces to a source. See the full breakdown →

What's open right now

Restaurants, shops, and hotels are reopening steadily — smaller, code-compliant storefronts first — and the mix changes month to month. Rather than publish a business list that would be out of date within weeks, we point you at the source that's actually maintained day to day:

See the Chamber's current open-business list →

Source: Greater Fort Myers Beach Chamber of Commerce — Who's Open. We link it rather than copy it because they update it and we can't verify every business daily — and a stale “open” is worse than no list at all.

Civic & infrastructure

Fort Myers Beach Pier

Approved

The island's most-asked-about project. Lee County awarded an $11.7 million construction contract in April 2026, federal permits were announced as approved at the end of June 2026, and the rebuilt pier is expected to take about a year to build — putting completion in 2027. The replacement is meaningfully bigger than the pier Ian destroyed.

Length
1,000 feet (about 70% longer than the old pier)
Width
12 feet (about 50% wider)
Contract
$11.7 million
Contractor
RJ Gorman Contracting LLC
Funding
$7M Tourist Development Tax (visitor 'bed tax') + $4.7M Florida Division of Emergency Management
Federal permits
Announced approved, June 30, 2026
Expected completion
2027
Amenities
ADA access, bench seating, turtle-friendly lighting

Full pier rebuild breakdown →

Sources (4) · verified July 21, 2026

Big Carlos Pass Bridge

Complete

The Big Carlos Pass project — the bridge at the island's south end connecting toward Lovers Key and Bonita — was marked with a ribbon-cutting on June 30, 2026. Access infrastructure matters enormously on a barrier island with only two ways on and off.

Ribbon cutting
June 30, 2026
Why it matters
South-end access route for the island
Sources (1) · verified July 21, 2026

Beach renourishment

Complete

Major sand placement rebuilt the beach berm and widened the shoreline, with dune stabilization and vegetation work continuing on select segments. Reporting in 2026 describes the beach itself as being in as good or better shape than before the storm — the island's single most-visited asset is back.

Scope
Berm rebuild, widened beach, dune stabilization
Status
Largely complete; vegetation work ongoing
Sources (2) · verified July 21, 2026

Commercial

Times Square — first approved rebuild

Approved

In January 2026 the town approved the first permanent new building in Times Square since Hurricane Ian erased the district: a three-story project with an open-air ice cream shop at street level and a one-bedroom residence above. Modest in size, but a genuine milestone — it's the first structure to clear the town's post-Ian standards in the island's commercial heart.

Approved
January 2026
Type
Three stories — open-air ice cream shop + one-bedroom residence
Why it matters
First permanent Times Square building approved since Ian
Sources (2) · verified July 21, 2026

Times Square — mixed-use development

Proposed

Developer Shlomo Melloul filed plans in 2026 for a three-story building spanning two Times Square parcels, proposed to include retail, a restaurant, and a rooftop bar. Filed plans are not approvals — this one is worth watching as it moves through the town's process.

Filed
2026
Scope
Three stories across two Times Square parcels
Proposed uses
Retail, restaurant, rooftop bar
Status
Plans filed — not yet built
Sources (1) · verified July 21, 2026

Hospitality

Margaritaville Beach Resort

Open

The 254-room resort opened in December 2023 — the first large-scale hospitality anchor of the island's recovery, and the project that proved major investment would return to Fort Myers Beach. It has now operated through multiple seasons.

Opened
December 2023
Rooms
254
Significance
First major post-Ian hospitality anchor
Sources (1) · verified July 21, 2026

What's honestly not back yet

Lodging inventory remains below pre-Ian totals. Times Square is a construction site with one approved building and more in the pipeline, not a rebuilt district. The pier is a 2027 story, not a today story. Some parcels still sit empty while owners decide. We say all of this plainly because the case for this island doesn't need exaggeration — and because you'll find out anyway when you visit.

Want the underlying construction data instead of the summary? The permit tracker updates daily from town records. For how the island got here, read the island's history. Every status above carries its verification date — if something looks stale, tell us.